TBM Mary is halfway her journey

11 January 2019

Mary, National Grid’s 510 tonne tunnel boring machine, is now halfway through her 5 km journey under the River Humber. Over 12,000 concrete segments have been fitted into place during 200,000 hours of work. The 3.65 metre diameter tunnel will house a vital replacement gas pipeline which will carry around 20% of the gas Britain needs, supplying homes and business across the east of England and beyond.

National Grid’s 510 tonne tunnel boring machine is now halfway through her epic 5km journey under the River Humber, major milestone in the project to secure 20% of Britain’s gas supplies.

The 160-metre-long machine, named Mary after Mary Fergusson, the first female fellow of the Institution of Civil Engineers, reached the halfway point on her journey from Goxhill to Paull at 2.30am on Tuesday 8 January, giving National Grid and their joint venture contractors Skanska, PORR Bau GmbH and A.Hak cause for celebration.

It has taken 200,000 man hours to get the tunnel to this stage, with a total of 2,023 concrete rings, each consisting of six segments, being put in place behind the machine as she tunnels 35 metres below the bed of the river.

Steve Ellison, Project Manager said: “Mary has done a brilliant job to date and we and our contractors are delighted to have reached the halfway point on the tunnel. There is still a lot more work to, do but I would like to say a big thank-you to the 40-strong team of engineers who have worked around the clock in very challenging conditions to get us to this important milestone.’

‘As you would expect, safety is our prime concern. All plant has a fire suppressant system, conditions in the tunnel are monitored along its entire length and we have regular emergency exercises and employ an on-site emergency team.’

Once the tunnel is finished, and Mary is removed from the tunnel via a shaft on the opposite bank of the river at Paull, the work on the next phase of the project will begin A new 42inch diameter gas pipeline will be laid inside the tunnel. This will replace the existing gas pipeline which currently crosses the river and is laid in a trench just below the river bed.

This pipe at risk of being exposed by shifting tides. Work has been carried out to keep it buried but the Humber Pipeline Replacement project offers a long-term solution.

Already, the eight ‘strings’ or sections of gas pipe which will be pushed into the tunnel have been laid out and welded on a vast pipe ‘field’ on the Goxhill site. Work to install them in the tunnel will take around a year to complete.

  • news

    Pipeline construction in France Pipeline construction in France

    Pipeline construction in France

    GRTgaz has been a valued French client of A.Hak for many years. Two recent projects, Arc de Dierrey and Val de Saône, have been portrayed in an impressive way.

  • news

    Safe re-start in the new year Safe re-start in the new year

    Safe re-start in the new year

    With a Safety Day for the entire team in Albania, the new year on the TAP project started with a renewed focus on safety.

  • news

    Drone images River Humber Gas Pipeline Replacement Project Drone images River Humber Gas Pipeline Replacement Project

    Drone images River Humber Gas Pipeline Replacement Project

    Watch the site of the River Humber Gas Pipeline Replacement Project from above.

  • news

    Winner ISTT No-Dig Award 2016 Winner ISTT No-Dig Award 2016

    Winner ISTT No-Dig Award 2016

    A.Hak Leidingbouw wins ISTT No Dig Annual Award 2016 in the category for Project Rehabilitation with the Unique pipe-in-pipe project for NAM.