TBM Mary is halfway her journey

11 January 2019

Mary, National Grid’s 510 tonne tunnel boring machine, is now halfway through her 5 km journey under the River Humber. Over 12,000 concrete segments have been fitted into place during 200,000 hours of work. The 3.65 metre diameter tunnel will house a vital replacement gas pipeline which will carry around 20% of the gas Britain needs, supplying homes and business across the east of England and beyond.

National Grid’s 510 tonne tunnel boring machine is now halfway through her epic 5km journey under the River Humber, major milestone in the project to secure 20% of Britain’s gas supplies.

The 160-metre-long machine, named Mary after Mary Fergusson, the first female fellow of the Institution of Civil Engineers, reached the halfway point on her journey from Goxhill to Paull at 2.30am on Tuesday 8 January, giving National Grid and their joint venture contractors Skanska, PORR Bau GmbH and A.Hak cause for celebration.

It has taken 200,000 man hours to get the tunnel to this stage, with a total of 2,023 concrete rings, each consisting of six segments, being put in place behind the machine as she tunnels 35 metres below the bed of the river.

Steve Ellison, Project Manager said: “Mary has done a brilliant job to date and we and our contractors are delighted to have reached the halfway point on the tunnel. There is still a lot more work to, do but I would like to say a big thank-you to the 40-strong team of engineers who have worked around the clock in very challenging conditions to get us to this important milestone.’

‘As you would expect, safety is our prime concern. All plant has a fire suppressant system, conditions in the tunnel are monitored along its entire length and we have regular emergency exercises and employ an on-site emergency team.’

Once the tunnel is finished, and Mary is removed from the tunnel via a shaft on the opposite bank of the river at Paull, the work on the next phase of the project will begin A new 42inch diameter gas pipeline will be laid inside the tunnel. This will replace the existing gas pipeline which currently crosses the river and is laid in a trench just below the river bed.

This pipe at risk of being exposed by shifting tides. Work has been carried out to keep it buried but the Humber Pipeline Replacement project offers a long-term solution.

Already, the eight ‘strings’ or sections of gas pipe which will be pushed into the tunnel have been laid out and welded on a vast pipe ‘field’ on the Goxhill site. Work to install them in the tunnel will take around a year to complete.

  • news

    Royal visit for Team Humber Royal visit for Team Humber

    Royal visit for Team Humber

    This week, Princess Anne visited the River Humber Gas Pipeline Replacement Project. With her visit she gave royal approval to this complex project that is of great importance to her country.

  • projects

    Water for Saudi Arabia Water for Saudi Arabia

    Water for Saudi Arabia

    A.Hak is known for it's expertise when it comes to the construction of water transport pipelines. A.Hak International proved this once again in Riyadh.

  • news

    Considerate Constructors Award for Team Humber Considerate Constructors Award for Team Humber

    Considerate Constructors Award for Team Humber

    Team Humber has reason for celebration. On Wednesday 27 March, the 2019 Silver Considerate Constructors Award was collected. A great achievement of the joint venture consisting of A.Hak, Skanska and PORR.

  • news

    Successful drilling Alkmaar Heat Network Successful drilling Alkmaar Heat Network

    Successful drilling Alkmaar Heat Network

    As part of the construction of the Alkmaar Heat Network, A.Hak performed a successful drilling under the Westtangent in Heerhugowaard on Tuesday, April 17th.